JNNSM: Phase 1 Batch 1, project status and tariff reduction numbers

 

Scheme
Projects allotted
Projects Commissioned
Weighted Average bid tariff
% Reduction in tariff
No.
MW
No.
MW
Large PV projects through NVVN
30
150
26
130
12.16
Rs. / Unit
32 %
2 Projects Cancelled
Migration Scheme
SPV
13
54
11
48
ST
3
30
1
2.5
RPSSGP Scheme (PV)
78
98
67
85.8
Solar Thermal projects through NVVN
7
470
Scheduled for  commissioning by May 2013
11.48          Rs. / Unit
25 %
Total
131
802
102
266.3

 

 

About Ritesh Pothan

Ritesh Pothan, is an accomplished speaker and visionary in the Solar Energy space in India. Ritesh is from an Engineering Background with a Master’s Degree in Technology and had spent more than a decade as the Infrastructure Head for a public limited company with the last 9 years dedicated to Solar and Renewable Energy. He also runs the 2 largest India focused renewable energy groups on LinkedIn - Solar - India and Renewables - India
This entry was posted in JNNSM, PV, Renewables, Solar, Solar Thermal and tagged , , , , , , , , , , , , . Bookmark the permalink.

2 Responses to JNNSM: Phase 1 Batch 1, project status and tariff reduction numbers

  1. Pingback: Grid-connected rooftop and off-grid solar to get greater push in JNNSM Phase II | Natural Group

  2. Pingback: A report on Rooftop Solar PV in India – Potential and Possible Solutions | Natural Group

Comments are closed.